Electricity generated from the first unit of Rooppur Nuclear Power Plant is likely to be experimentally connected to the national grid within the current month of November, provided all technical arrangements proceed without hitch.

Multiple sources associated with the project informed the media that preparations are underway to connect the electricity produced from the first unit to the grid by the end of November, provided no technical complications or unwanted situations arise.

Preliminary activities for experimental generation have already been advanced, alongside ongoing coordination efforts across various technical systems.

An initial target of supplying 300 megawatts (MW) of electricity has been set for the primary stage, which requires approval from Bangladesh Atomic Energy Regulatory Authority (BAERA).

Mahmudul Hasan, chairman of Bangladesh Atomic Energy Regulatory Authority (BAERA), informed that a specific timeframe for commencing electricity supply to the national grid cannot be confirmed at present.

Advertisement
Advertisement

However, he said efforts are being made to begin operations as quickly as possible.

Following the experimental connection, every stage of production and supply will be closely examined, and the formal inauguration will take place only after confirming that there are no apparent problems.

The BAERA chairman expressed hope that Prime Minister Tarique Rahman might attend the inaugural ceremony as the chief guest. He added that president of Russia Vladimir Putin is also likely to join the ceremony via video conference.

Read more

Taking into account the participation of top leadership from both nations, relevant sources mentioned that plans are being made for a formal inauguration in December, although the exact date has not been finalised.

The chairman further explained that the inauguration schedule depends on when the prime minister can allocate time for the event, making it impossible to announce a specific date immediately.

According to him, once the initial supply of 300 MW from the first unit begins, production will be expanded gradually.

However, generating power at full capacity and supplying that entire volume to the national grid may take another five to six months, with full-capacity connection expected between April and June next year.

According to project sources, when the thermal capacity of the first unit’s reactor reaches 40 per cent, it will be possible to generate approximately 30 to 35 per cent of its full capacity, aligning with the plan to supply around 300 MW to the grid in the initial phase.

Advertisement
Advertisement

Regular supply will not commence immediately after the initial grid connection, as generation and transmission will be closely monitored for several days after the experimental link to check for any defects or technical issues.

Necessary approval will be obtained from BAERA if all results are satisfactory, following which the official inauguration of electricity supply operations may take place.

Rooppur Nuclear Power Plant is being constructed at Ishwardi in Pabna with Russia’s most modern nuclear technology, financing, and technical assistance.

The project is being implemented by Atomstroyexport, the engineering division of Rosatom, the state atomic energy corporation of Russia.

The plant comprises two units with a capacity of 1,200 MW each, which will supply a total of 2,400 MW of electricity to the national grid once both units become operational at full capacity.