Electricity from Rooppur to enter national grid

Electricity from Rooppur to enter national grid
Rooppur Nuclear Power Plant. Photo: Collected
Advertisement
Advertisement
Advertisement
Advertisement

Power Grid Bangladesh PLC has achieved full capability to safely transmit electricity from the first unit of the Rooppur Nuclear Power Plant to the national grid.

On Monday at 3:32pm, the company reached this milestone by successfully launching the “Rooppur-Gopalganj 400 kV transmission line.”

In a press release, the Power Grid authorities stated that this marks a significant advancement toward transmitting electricity from the country’s first nuclear power project.

Advertisement
Advertisement

The 158-kilometer-long Rooppur-Gopalganj transmission line contains a total of 414 towers. Through this line, electricity from Rooppur’s first unit can now be safely supplied to the national grid.

Related News

Earlier, two other high-voltage transmission lines were launched to ensure the “physical startup” of Rooppur’s first unit. Among them, the “Rooppur-Baghabari 230 kV transmission line” was launched on June 30, 2022, and the “Rooppur-Bogura 400 kV transmission line” was launched on April 30, 2024.

With the new line in operation, a total of three transmission routes are now active for the Rooppur plant, each with a capacity to carry 2,000 megawatts of electricity.

With all three lines fully operational, a practical infrastructure is now in place for uninterrupted supply of electricity from the Rooppur Nuclear Power Plant to the national grid. This marks a major achievement in the country’s energy security and technological capability.