Electricity generated from the first unit of Rooppur Nuclear Power Plant, Bangladesh’s maiden nuclear power facility, was experimentally connected to the national grid on Tuesday.
A total of 350 megawatts (MW) of electricity was transmitted at 3:16pm in the presence of Minister for Science and Technology Faqir Mahbub Anam.
Senior Scientific Information Officer Saikat Ahmed confirmed the development in a press release, describing it as a key milestone in the power plant’s generation and grid synchronisation efforts.
Under the trial connection plan, electricity will be supplied to the national grid for approximately 8 to 10 hours.
During this timeframe, crucial technical tests, including assessing the stability, effectiveness, and integrated operation of the turbine, generator, and national grid, will be conducted.
Subsequently, the power plant will be disconnected from the grid to carry out various technical evaluations.
Following an intermission of roughly 28 hours, the facility will be reconnected to the grid for another 4 to 6 hours to complete required technical and operational tests.
At every testing phase, the performance of the plant’s various systems, turbine and generator efficiency, and coordination with the national grid will be closely verified.
Once all technical test results prove satisfactory and scheduled tasks at this stage are completed, approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) will be required for the next phase of trial operations.
Subject to BAERA’s approval, the plant will be reconnected for trial operations to proceed with the next steps of electricity supply.
According to the contract signed with the Russian contractor, commercial power supply at full capacity from the first unit will begin permanently upon completing a 10-month trial operation period.
The Rooppur Nuclear Power Plant consists of two units, each with a generation capacity of 1,200MW, giving the facility a total capacity of 2,400MW. The plant is expected to make a vital contribution towards fulfilling the country’s growing electricity demand, ensuring energy security, and producing sustainable power.
This experimental grid connection represents a historic milestone in the progress of Bangladesh’s power and energy sector, advancing the nation another step forward in nuclear technology-based power generation.