Advertisement

Chattogram Port congestion raises demurrage, price fears

Vessels wait 3-4 days; container stocks up 9.91%

Chattogram Port congestion raises demurrage, price fears
Chattogram port. File Photo: Zakir Hossain/TIMES
Advertisement
Advertisement

Congestion at Chattogram Port is intensifying, with vessels waiting three to four days at the outer anchorage, adding $15,000-$20,000 a day in costs and raising fears that the extra expense will feed through to consumer prices.

Chittagong Port Authority (CPA) data show vessels at the jetties and outer anchorage rose from 62 on 25 October to 91 on 25 November, up 29 vessels or 46.8 per cent in a month.

Container ships waiting at the anchorage went from none to seven. Container stocks in the yards rose 9.91 per cent, from 42,141 TEUs to 46,316 TEUs, an increase of 4,175 TEUs, occupying around 78.5 per cent of total yard capacity of approximately 59,000 TEUs.

Senior officials of several shipping lines told TIMES that container vessels are waiting three to four days, with additional daily costs of $15,000-$20,000 depending on vessel size, while delay-related charges for large mother vessels can reach up to $30,000 a day. Industry insiders fear these costs will be reflected in import prices.

Advertisement
Advertisement

Stakeholders attribute the pressure to higher imports ahead of Ramadan, a shortage of lighter vessels, operational challenges after the CCT operator change and constraints in equipment and manpower.

Everest Port Services Limited took over CCT operations from Saif Powertec on 24 November. Shipping lines reported disruptions, citing shortages of gantry crane and RTG operators, inadequate trailers, damaged yard equipment and congestion in the import container yard at CCT and the New Mooring Container Terminal. They claim waiting times there have risen to three to four days, against around one day at the General Cargo Berth.

Read more

The Department of Shipping says around 1,000 lighter vessels- nearly half the fleet carrying cargo from Chattogram Port- are stranded at river ports and jetties, making it hard for mother vessels to unload and leave on schedule.

Bangladesh Shipping Agents Association President Md Salah Uddin Chowdhury said changes in terminal management could affect vessel handling, and cited lighter vessel shortages and fitness or certification problems as contributing to delays. Delays beyond the stipulated period could cause substantial losses for shipowners and charterers, he said.

Advertisement
Advertisement

At the 21 private inland container depots, BICDA data show 10,266 TEUs of export-laden, 9,852 TEUs of import-laden and 50,610 TEUs of empty containers as of 8:00am on 25 November. In the preceding 24 hours, 1,901 TEUs were dispatched to the port against a daily average of 2,000-2,200 TEUs, while 1,123 TEUs of import containers were delivered.

Advertisement
Advertisement

BICDA Secretary General Ruhul Amin Sikdar said export stocks were slightly above normal and imports had risen.

Chittagong Customs Agents Association Executive Member and Chittagong Chamber of Commerce and Industry Director Sarwar Alam Khan said imports had recovered ahead of Ramadan, though deliveries had increased in the past two to three days.

CPA Secretary Syed Refayet Hamim said the operator change might have caused temporary disruption but cargo handling remained normal, and said he would consult the terminal manager for further information.